your question

How many days does it take to produce a shirt?

The duration is determined by the product, sample, fabric preparation and order distribution. It would be misleading to say a single number of days without seeing this information. Share your target date and let's set up the applicable calendar together.

Review the order and delivery process
01

Delivery time does not only consist of planting days

Fabric and accessory supply, sample revision, brand approval, cutting preparation, production, final control and packaging are parts of the same calendar. If one of these is based on assumption, the delivery date should be stated conditionally.

02

Under what conditions is the preliminary estimate confirmed?

The preliminary estimate from the initial discussion is reassessed once material availability, sample approval, the final order breakdown and production schedule availability have been verified. If sourcing or brand feedback is pending, the date must be recorded together with that condition.

If a revision changes the pattern, material or sequence of operations, the affected preparation and approval steps are reassessed; the previous date is not assumed to remain valid until a new date has been confirmed in writing.

Factory flow in shirt production plan
Factory flow in shirt production plan
Review the order and delivery process
03

How does order scale change the plan?

Number of preparations and changes for small, multi-model orders; For large orders, capacity, line balance and intermediate control plan come to the fore. In case of reorder, approved records can speed up the process, but the material lot must be re-verified.

04

Readiness-for-dispatch and receipt dates

The date when goods are ready for dispatch is not the same as the date when the buyer receives them. Transport, customs clearance and the destination warehouse's receiving schedule are assessed separately. Share the target warehouse arrival date and delivery point; match responsibility for these stages to the written delivery terms.

05

Assess delivery dates against production requirements

Erten Tekstil creates the delivery plan for brand-specific shirt production according to product, quantity, material and approval status. You can request calendar availability by sharing your target sales period and finalized decisions in the form.

06

Pre-order checklist

Estimate

Pending sourcing and approval conditions

Revision

Affected operation and reconfirmed date

Enthusiasm

Readiness after inspection and packing

Arrival

Transport, customs clearance and warehouse receiving

07

How do we approach this issue at Erten?

We assess lead time based on material preparation, sample approval and production availability. We discuss the target for readiness for dispatch separately from transport and receipt conditions.

Guide topic: Erten Tekstil product development, production and quality approach. Production feasibility is assessed separately using the product and order details.

Frequently asked questions about this topic

Is the delivery date finalized at the first meeting?

If there is not sufficient product, material and order information, only a preliminary estimate can be given; The plan becomes final as critical approvals are completed.

Can sample changes affect the delivery date?

Depending on the scope of the revision, the material, pattern or operation plan may change and the schedule is re-evaluated.

Let's see together

Let's talk about your product.

Write down your target delivery date and sample status; Let's determine the decision points on the calendar together.

It is not necessary to have all the details ready at the initial consultation.