your question

We approved the sample; Can production start immediately?

It's good to first check that the production team is using the same sample, size chart and material version. If there is a clear decision, let the responsible person be clear; Let's compare the first product with the approved reference.

Examine the mass production approach
01

Purpose of the pre-production meeting

The pre-production meeting transforms design and sample decisions into a common instruction to be applied in mass production. The aim is not to reread old correspondence; it is to finalize on a single record which product version, size chart, material, and packaging information the production will start with.

If there is an open decision at the end of the meeting, the responsible party and the closing date should be specified. Initial assumptions should not be made without resolving uncertainties affecting production.

02

Inputs to be verified at the same table

The product file and the physical sample must belong to the same revision. Fabric, interlining, button, label, and packaging codes must match the definitions that the purchasing and production teams will use.

  • Approved sample and measurements table
  • Model, color, size, and quantity distribution
  • Fabric and accessory codes
  • Critical seams and viewpoints
  • Folding, labeling, and packaging instructions
Shirt production line preparation
Shirt production line preparation
Examine the mass production approach
03

How should the initial production output be evaluated?

The initial production output should be compared not only in terms of general appearance but also through critical dimensions, part placement, seam balance, accessory accuracy, and label information. If there are findings, the affected operation and the correction to be applied are recorded before production continues.

This check is not a new design round. It is a gateway that verifies that the approved standard is correctly interpreted and repeatable in the production line.

04

Controlled mass production start

Before bulk production begins, Erten Tekstil clarifies the approved product information and the control points for each private-label shirt order. Share how many styles you have, their approval status and your target production period to request an initial feasibility review.

05

See the same in the table before deciding.

Reference

Approved sample and technical file version

Input

Material, quantity, and operational information

Review

Initial production measurement and workmanship comparison

Start

Closing open decisions and written release

06

How do we approach this issue at Erten?

The start of mass production is planned after it is verified that different teams are using the same approved product version and the same control criteria.

Content review area: Erten Tekstil product development, production and quality approach. Commercial suitability is also evaluated based on product and order information.

Frequently asked questions about this topic

Does the pre-production meeting replace sample approval?

No. Sample product decisions are validated; pre-production meetings finalize which records and responsibilities will be transferred to mass production teams based on approved decisions.

Can changes be requested in the first production control?

If there is a difference in application according to the approved standard, the correction is recorded. If it is a new design or material change, it should be evaluated separately with cost, schedule and re-approval effect.

Let's see together

Let's talk about your product.

Share your approved sample and target production period; Let's see together the decisions that remained open at the beginning.

It is not necessary to have all the details ready at the initial consultation.